整套的電纜橋架的敷設(shè)安裝流程
在電纜橋架安裝完成后,就要進(jìn)行電纜的鋪設(shè),山東電纜橋架公司提示大家,電纜鋪設(shè)我們要進(jìn)行檢查,嚴(yán)格按照規(guī)定程序進(jìn)行,保證施工的質(zhì)量和日后使用的可靠性。
After the installation of cable bridge is completed, cable laying should be carried out. Shandong Cable Bridge Company reminds you that cable laying should be inspected and carried out in strict accordance with the prescribed procedures to ensure the quality of construction and the reliability of future use.
一套合理的電纜橋架鋪設(shè)順序是這樣的:
A reasonable sequence of cable bridge erection is as follows:
1、測量定位,確定安裝橋架的支架安裝位置,經(jīng)檢查確認(rèn)支架合格后,才能安裝橋架;
1. Measure and locate the position of the bracket to install the bridge. After checking and confirming that the bracket is qualified, the bridge can be installed.
2、橋架安裝后也要經(jīng)過檢查,只有合格后才能進(jìn)行電纜的敷設(shè);
2. After the installation of the bridge frame, it should also be checked. Only after qualified can the cable be laid.
3、對于電纜,在敷設(shè)前進(jìn)行絕緣測試合格,才能敷設(shè);


3. For cable laying, the insulation test is qualified before laying.
4、電纜電氣交接試驗(yàn)合格,且對接線去向、相位和防火隔堵措施等檢查確認(rèn),才能通電。
4. Electrical connection test of cable is qualified, and check and confirm wiring direction, phase and fire-proof and blocking measures, etc. before power can be turned on.
以上的內(nèi)容由山東電纜橋架公司友情提供,更多精彩內(nèi)容請收藏我們的官網(wǎng):http://www.lfrail.com謝謝支持。
The above content is provided by the friendship of Shandong Cable Bridge Company. For more wonderful content, please collect our official website: http://www.lfrail.com. Thank you for your support.
上一篇:電纜橋架安裝常見質(zhì)量缺陷問題
下一篇:山東電纜橋架接地電阻的注意事項(xiàng)
下一篇:山東電纜橋架接地電阻的注意事項(xiàng)
相關(guān)文章 / Recommended news
- 山東電纜橋架:金屬線槽橋架安裝工藝要點(diǎn)!
- 濟(jì)南電纜橋架:電纜橋架常用的安裝方式及安裝單價(jià)分享
- 山東電纜橋架:設(shè)計(jì)施工時(shí)金屬橋架怎么接地?
- 濟(jì)南電纜橋架:橋架外形尺寸允許偏差要求
- 山東電纜橋架:一文讀懂國標(biāo)電纜橋架厚度規(guī)定
- 濟(jì)南電纜橋架:關(guān)于電纜橋架接地問題應(yīng)對措施
- 山東電纜橋架:槽式橋架與托盤式電纜橋架的區(qū)別
- 山東電纜橋架:槽式橋架與托盤式電纜橋架的區(qū)別
- 濟(jì)南電纜橋架:電纜橋架的分類、材質(zhì)、組合結(jié)構(gòu)和產(chǎn)品介紹
- 山東電纜橋架的接地非常重要及接地注意事項(xiàng)